Work to be carried out
Regarding the landfill restoration project, according to the announcement of the open online tender, the subject of the contract is the transportation and integration of 90,000 m3 of waste, of which 80,000 are unsorted and 10,000 are packaged, within the cells of the Corfu landfill, from the site designated for the construction of the Corfu Municipal Solid Waste Treatment Plant.
These had been temporarily deposited at various times in the past; however, since no action was taken for their removal, they eventually evolved into a long-standing open wound.
In parallel, within the framework of the project, works will be carried out to ensure the stability of the landfill relief for the environmental upgrade of the landfill. The contract in its entirety has a completion time of six months from its signing.
The project has secured funding of 1 million Euros from the credits of the Ministry of Interior's Public Investment Programme for Natural Disasters (Ballοs), as well as an environmental permit.