Σάββατο 27.07.2024 ΚΕΡΚΥΡΑ

North Corfu road and water supply works progressing

North Corfu
24 Οκτωβρίου 2023 / 16:30

CORFU. North Corfu Municipality is continuing at pace with projects of vital importance for its local districts.

(NORTH CORFU MUNICIPALITY) Water supply and road construction projects in the Municipality of North Corfu are being completed at pace.

True to its commitments, the Municipality is continuing at pace with projects of vital importance for its local districts. The efforts of the municipal authority, with the assistance of its Technical Services, aim to maintain the condition of the road network at a high level, providing maximum support for its maintenance, primarily focusing on its safety and subsequently ensuring its optimal functionality.

A) Road Network Maintenance and Restoration Works in Kassopi, Thinalio, Agios Georgios, Esperion with a budget of €2m (including VAT):

  • Work on the municipal road ARILLAS - AKROTIRI (Magoulades community) has been COMPLETED.

  • Work on the municipal road AGONARI - VELONADES (Agrafon-Velonades communities) has been COMPLETED.

  • Work on the municipal road RODA-AGRAFI is in progress.

 

B) As part of the work to address the longstanding water supply issues in the Municipality of North Corfu, drilling has commenced at AEVEK, while

C) the replacement of the water supply network on the central road of Acharavi - Roda is continuing, providing a solution to the recurring damage to the main pipeline and the serious water supply issues in the broader area.