The Project
The project for the redevelopment of the Garitsa - Anemomylos Park was contracted on 12-01-2022 for the amount of €1,142,834.29 (after deducting the bidder's discount of 45.12%). It involved low-key work aimed at revitalising and modernising the park to make it functional and aesthetically attractive.
Its execution time was set for 15 months from the contract date, i.e., by 12-04-2023. However, three extensions were granted in total upon the contractor's request, with the latest one being for February 28, 2024. Essentially, this extension was required, withoutdue to no fault of the contractor's, because the process of drafting and approving the 2nd Summary Table of Works (APE) by the Municipality's Services was pending. However, the issue has already been resolved, as the draft of the 2nd APE was recently approved by the Municipal Committee, so the contractor's payment will be made after the certification of the completed works.